Our Works
CEBU‐NEGROS‐PANAY 230KV BACKBONE PROJECT STAGE: 3 SUBMARINE (CEBU – NEGROS LINK)
SAN ISIDRO, CALATRAVA, NEGROS OCCIDENTAL
Cable Laying Of 230kv Submarine Cable And Construction Of Cable Terminal Station (CTS)
Completion Date: August 30, 2021
CEBU‐NEGROS‐PANAY 230KV BACKBONE PROJECT STAGE: 3 SUBMARINE (CEBU – NEGROS LINK)
TALAVERA, TOLEDO CITY, CEBU
Cable Laying Of 230kv Submarine Cable And Construction Of Cable Terminal Station (CTS)
Completion Date: August 30, 2021
CEBU‐NEGROS‐PANAY 230KV PROJECT STAGE: 2
TALAMBAN, CEBU
Installation Of 230kV Cable
ASIAN ALCOHOL CORPORATION
BRGY. CANJUSA, PULUPANDAN, NEGROS OCCIDENTAL
Installation Of Electrical And Instrumentation Works
LEYTE SOLAR FARM
DOLORES, ORMOC CITY, LEYTE
Design, Engineering, Procurement & Construction contract
ENERVANTAGE DIESEL POWER PLANT
CAPELCO COMPOUND, PANIT-AN, CAPIZ
The O&M contract is for 20 years in the maintenance, operation and upgrade work of the Diesel Power Plant.
BUKIDNON POWER CORPORATION
BARANDIAS, PANGANTUCAN, BUKIDNON
Design, Engineering, Procurement, Construction, Operation & Maintenance contract for a 2 x 2.4 MW Diesel Power Plant